| Hard cost line | $M |
|---|---|
| Hard cost subtotal | 166.0 |
| Soft costs (14%): design, permits, PM, insurance | 23.2 |
| Design contingency (4%) | 7.6 |
| Construction contingency (5%) | 8.3 |
| Escalation to construction midpoint | 18.0 |
| Capital cost (public estimate) | 223.1 |
| Capital cost after DB savings | 209.8 |
| Interest during construction | 14.6 |
| Bid costs & developer fee | 4.2 |
| Priced construction risk | 16.9 |
| Less public milestone payment (40%) | −83.9 |
| Privately financed | 161.6 |
An illustrative model for discussion, built on the usual shape of a US availability-payment P3: a public sector comparator, risk-adjusted net present values, a milestone payment at substantial completion and a CPI-indexed availability payment with performance deductions. Every number is editable and saves in this browser. Figures are a fictional example, not a real procurement.